Installation & Swap-Out Checklist

Minimizing Downtime During the Changeover

Overview

The gap between disconnecting the old chiller and starting up the new one is where downtime risk concentrates - plan that window deliberately.

Confirm the new unit's electrical and piping connections match (or have been adapted to match) the existing infrastructure before the old chiller is disconnected - re-terminating a mismatched electrical service or re-routing piping after the old unit is already out extends downtime that could have been avoided with a pre-check. If the new unit's footprint or connection points differ from the old one, that adaptation work should happen before, not during, the swap.

The old unit's refrigerant needs to be recovered by a licensed technician before disposal, regardless of refrigerant type - this is a regulatory requirement, not optional, and it's worth scheduling as its own step rather than assuming it happens automatically during removal. For an R-22 unit specifically, recovered refrigerant may have real reclaim value, which is worth asking your service contractor about rather than treating it as waste.

Plan the actual downtime window realistically: disconnection, rigging the old unit out, positioning and connecting the new one, and startup/commissioning all take real time, and a process that can't tolerate an extended cooling gap may need a temporary bridge chiller (arranged by the site or its contractor - see Emergency & Backup Cooling for Critical Spaces under Medical & Healthcare for the connection planning) for the changeover window.

  • Confirm electrical and piping connections match before disconnecting the old unit
  • Refrigerant recovery by a licensed technician is a regulatory requirement, not an optional step
  • A process that can't tolerate a cooling gap may need a temporary bridge chiller during the swap

Downtime is decided before the old unit is disconnected.

Confirm electrical, piping, pad footprint and rigging access while the old chiller is still running. A mismatch found mid-swap costs the most, because the process is already offline and waiting.

The Swap-out Sequence

Before Disconnect

  • New unit's electrical service confirmed to match (voltage, phase, breaker size)
  • Piping connections and pad footprint confirmed or adapted
  • Refrigerant recovery technician scheduled for the old unit
  • Rigging or crane access confirmed for both units
  • Bridge chiller arranged, if the process can't tolerate a gap

Disconnect Through Startup

  • Refrigerant recovered and old unit disconnected
  • Old unit rigged out; new unit positioned on the pad
  • Electrical, piping and controls connections made
  • Startup and commissioning performed, setpoint verified
  • Old unit removed from site for disposal or resale

Where the Schedule Actually Slips

Most swap-out delays trace back to one of two causes: a connection mismatch discovered after the old unit is already disconnected, or a rigging access problem that wasn't scoped before the crew showed up. Both are avoidable with the pre-check step, and both are expensive precisely because they're discovered mid-swap, when the process is already offline and waiting.

The second most common delay is controls integration - if the new unit ties into a building management system or a process controller the old one didn't, budget extra commissioning time for that specifically, rather than assuming startup covers it automatically.

Swap-Out Day: Downtime and Recovery Questions

Supply and return temperatures, flow and the setpoint it actually holds, taken at peak load, plus electrical readings and any alarm history the controller keeps. These give commissioning a baseline: if the new unit moves the same heat at the same setpoint, the swap is proven. As a check, 90 GPM with an 8°F drop is 360,000 BTU/hr, 30 tons on water. Photograph the nameplate, the wiring terminations and every pipe connection with a tape measure in the frame. List which control signals the old unit sends or receives, since those are what a controls integration has to reproduce on the new one.

Only after it has been tested, because a new evaporator is the wrong place to find out the old fluid is weak, dirty or past its inhibitor life. Check the concentration and the freeze point it gives, the inhibitor level, and the color and sediment in a sample. Fluid that passes can go back in, but plan where it will be held while the loop is open, since the whole loop volume has to go somewhere. Fluid that fails is better replaced with a fresh mix at the right percentage than topped up. Either way, fit or clean a strainer before the new unit starts.

That the new chiller holds setpoint under real process load, not just that it starts. Run it with the process at or near peak, confirm evaporator flow matches the design, and check the supply-to-return drop against the readings logged on the old unit. Prove each safety: flow switch, low-temperature cutout and any interlock with the process pumps. If the unit reports to a building management system or process controller, confirm every point reads correctly at the far end.