Chiller Sizing Calculator

Work the Numbers, or Send Them Straight to Us

Overview

The math behind a chiller rating is simple once you have the right inputs - the hard part is getting the heat load number right in the first place.

Working the calculation by hand takes three inputs: heat load in BTU/hr (convert tons to BTU/hr by multiplying by 12,000), your target flow rate in GPM, and the delta-T between supply and return fluid temperature. Divide heat load by (GPM x 500 x the glycol mix's specific heat factor) to solve for delta-T, or rearrange the same formula to solve for GPM if delta-T is fixed by the process.

A worked example: a fermentation load of 60,000 BTU/hr, running a 25% propylene glycol mix (specific heat factor roughly 0.95) at a 10°F delta-T, needs about 12.6 GPM - (60,000) / (10 x 500 x 0.95). That GPM and delta-T then set the target tonnage: 60,000 BTU/hr is 5 tons, so the chiller needs to be rated for 5 tons at whatever leaving fluid temperature the fermentation actually requires.

If you'd rather skip the math, send us the heat load (or the equipment specs that let us calculate it), your target fluid temperature, and indoor-vs-outdoor installation - we'll work the sizing and come back with a rating rather than asking you to run the numbers yourself.

  • Tons to BTU/hr: multiply by 12,000. BTU/hr to GPM: divide by (delta-T x 500 x specific heat factor)
  • Propylene glycol runs a specific heat factor of roughly 0.96 at 20%, 0.94 at 30% and 0.91 at 40%, vs. 1.0 for water
  • Sending us the heat load and target temperature gets a faster, more accurate rating than reverse-engineering a tonnage guess
1

Start with BTU/hr

Get the heat load from equipment data, not a guess

2

Fix one variable

Set delta-T or GPM and the other one falls out

3

Correct for glycol

Use roughly 0.91 to 0.96 for 20-40% propylene, not the 1.0 factor for water

4

Read off the tons

Convert the load to tons and confirm the loop GPM

Working Through a Sizing Scenario

The formula behind every rating is BTU/hr = GPM × delta-T × 500 × specific heat factor. Solve it for whichever variable your process fixes and the others fall out - a fixed delta-T tells you the GPM you need, a fixed GPM (say, from an existing pump) tells you the delta-T you'll get.

The specific heat factor is what most hand calculations get wrong: water is 1.0, but a propylene glycol solution runs from about 0.96 at 20% down to about 0.91 at 40%, so plugging in 1.0 for a glycol loop understates the flow you actually need by roughly 4-10%.

Send Us

  • Heat load (BTU/hr or tons) or the equipment data to calculate it
  • Target delta-T, if your process fixes one
  • Glycol mix percentage, or the coldest temperature the loop must survive
  • Target leaving fluid temperature
  • Indoor or outdoor installation

SAMPLE SIZING SCENARIOS

ScenarioHeat LoadDelta-TGlycol MixApprox. GPMTons Needed
Fermenter jacket cooling60,000 BTU/hr10°F25% propylene~12.6 GPM5 tons
Compressor jacket cooling120,000 BTU/hr15°F30% propylene~17 GPM10 tons
Plastics mold cooling300,000 BTU/hr8°F20% propylene~78 GPM25 tons

These are worked examples to show the math, not a lookup table for your own job - actual GPM and tonnage depend on your specific numbers.
Call and talk it through with an engineer: 1-805-484-2992.

Working the Sizing Math: Common Questions

No; with the heat load and target leaving fluid temperature we can pick a workable delta-T and the GPM follows from it. The choice still matters for the pump and piping. Take the compressor jacket example, 120,000 BTU/hr on its 30% mix, a 0.94 factor: a 15°F spread needs about 17 GPM, a 10°F spread about 26 GPM, and a 20°F spread about 13 GPM. It is 10 tons in every case; only the flow and the pipe sizes change. If your process does fix a spread, for instance because a jacket cannot tolerate a large temperature difference from top to bottom, tell us and we size around it.

About 0.6 GPM short, roughly 5%: the 60,000 BTU/hr fermenter at a 10°F delta-T works out to 12 GPM on water's 1.0 factor, against about 12.6 GPM at 0.95. The gap grows as the mix gets richer, because the factor falls as glycol percentage rises. A pump picked at 12 GPM on that loop either runs a wider spread than intended, about 10.5°F instead of 10°F, or leaves the jacket warm at peak fermentation. The error scales with load, so on the 25-ton plastics row, with its leaner 20% mix, it is about 3 GPM.

Yes, and we will quote against it, but we will also ask where it came from, because a bare tonnage is often carried over from an unrelated job. Checking it takes minutes. Take the plastics row: 25 tons is 300,000 BTU/hr, which at an 8°F spread on its 20% mix, a 0.96 factor, needs about 78 GPM. If your existing pump moves 78 GPM and the loop only shows a 4°F spread at full production, the real load is about 150,000 BTU/hr, or 12.5 tons. That one reading catches the most expensive kind of oversizing before it is ordered.

Because it's delta-T is narrower: 8°F against 15°F, so every ton needs more fluid to carry the same heat. Per ton, the formula gives 12,000 / (500 x factor x delta-T) GPM, which is about 3.1 GPM per ton at the plastics row's 8°F, 2.5 at the fermenter's 10°F and 1.7 at the compressor row's 15°F. The plastics row's 78 GPM for 25 tons and the compressor row's 17 GPM for 10 tons sit right on those figures. Mold cooling usually runs a tight spread to hold even part temperature across the mold, and the price of that is larger pumps, piping and connections for the same tonnage.